Kolkata Metro Expansion Faces Major Delays Due to Land and Clearance Issues, Railways Minister Informs Parliament

Date:

The Ministry of Railways has revealed to Parliament that several key expansion corridors of the Kolkata Metro are significantly delayed. The primary reasons cited include land acquisition hurdles, removal of encroachments, and pending clearances from the West Bengal Government.

Currently, 52 kilometers of new metro lines are under construction in and around Kolkata. However, as Railways Minister Ashwini Vaishnaw stated in a written reply in the Lok Sabha, approximately 20 kilometers of these projects remain stalled.

The Joka–Esplanade corridor, one of the crucial expansion lines, exemplifies these challenges. While the 7.74-km Joka–Majerhat section is operational, construction beyond Majerhat up to Esplanade continues to face delays.

A notable bottleneck has been land acquisition issues at Khidderpur, where land owned by the Kolkata Armed Police was required for the project. Approval for this land was pending for nearly five years and was only granted in July 2025, further pushing back progress.

Minister Vaishnaw’s disclosure underscores the complex administrative and logistical challenges facing urban infrastructure projects in the region, with hopes pinned on timely government cooperation to accelerate completion.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

spot_img

Popular

More like this
Related

Dietary Diversity, Maternal Nutrition Take Centre Stage in 9th National Nutrition Month

The country's 9th National Nutrition Month (Rashtriya Poshan Maah)...

503-Member Indian Contingent to Represent India at Asian Games 2026 in Japan

The Indian contingent for Asian Games 2026 was received...

Major Decision in UP: Doctors to Continue Serving Until 70

The state government has taken a major decision to...

BRICS at 20: A New Power Centre Taking Shape in the Global Economy

What began as an acronym coined by Goldman Sachs...